Before the installation of PVC flooring, a thorough site inspection is required to ensure that the base conditions meet construction standards. Only after these requirements are verified can the flooring installation begin. Below are the key inspections and considerations:
The ambient temperature during installation should be no lower than 15°C, and the floor surface temperature must be above 10°C.
Application and curing times for adhesives and primers are directly affected by temperature—higher temperatures shorten curing times, while lower temperatures extend them.
Since PVC flooring naturally expands and contracts with temperature fluctuations, it must be unpacked and placed on-site at least 24 hours before installation to acclimate and stabilize at room temperature.
Flatness is critical for achieving a smooth, long-lasting PVC floor finish. Inspections should be carried out using a 2-meter straightedge and feeler gauge:
Cement concrete base: Maximum gap must not exceed 4mm. If it does, apply a self-leveling cement layer.
Cement mortar base: Maximum gap must not exceed 3mm. Large-scale unevenness requires secondary leveling.
Flatness requirement: Within a 2-meter ruler, the variation must be less than 2mm.
The leveling layer must be smooth, solid, and free of bumps or depressions.
The base floor must have sufficient strength to support PVC flooring without risk of failure:
Cement concrete strength: ≥ C20.
Cement mortar strength: ≥ M15 (1:3 volume ratio).
Surface conditions: Must be free of sanding, hollowing, cracking, and excessive porosity.
Severe issues (hollowing, large cracks) must be repaired before installation.
Minor cracks can be treated with cement fillers and reinforced with steel bars if necessary.
Moisture is one of the most critical factors in PVC flooring installation:
Ground foundation moisture content: ≤ 3% by weight.
Air humidity: Between 20% and 75%.
If air humidity is high, use dehumidifiers or air conditioning to stabilize conditions.
If moisture content is >4%, apply an epoxy moisture-proof primer.
If moisture content is >8%, PVC flooring installation is not recommended until conditions improve.
The correct grade of primer, self-leveling compound, and adhesive must be determined based on:
The condition of the substrate.
The type of PVC flooring (tiles or roll flooring).
The expected traffic and load-bearing requirements.
Before installation, the substrate must be completely clean:
Remove all oil, wax, paint, pigments, and construction residues.
The floor must be free from dust and contaminants that could affect adhesive bonding.
To avoid damage to newly installed PVC flooring:
Cross-construction should be minimized.
If unavoidable, protective coverings must be applied to safeguard the floor until all works are completed.
Ambient and floor temperatures meet requirements.
Floor flatness within acceptable tolerances.
Substrate strength verified.
Cracks and defects repaired.
Moisture content ≤3%.
Primer, leveling, and adhesive chosen correctly.
Surface is clean and contamination-free.
Protective measures in place against cross-construction.
By following these inspections and preparation steps, PVC flooring installation will achieve maximum durability, stability, and aesthetic quality.
Why Emery PVC Flooring Rolls Are Replacing Rubber Flooring in Public Transportation
How to Choose the Right PVC Sports Flooring for Different Sports Venues
The Gym’s “Invisible Bodyguard”: Why Rubber Mats Are a Must-Have for Athletes
The Ultimate Guide to LVT Flooring: Installation, Maintenance, Pros, and Cons
Analysis of Causes of Bulging in PVC Flooring (Roll) - Must-Read
Precautions During the Processing and Use of Aluminum-Plastic Panels
Wood Veneer Panel Advantages and Disadvantages: A Clear Comparison with Melamine Board